Messina, extraordinary powers for the reclamation of the Falcata area: 22 million for the first phase

John

By John

Choose us on:

Google Discover

Google logo
Preferred Sources

Conference on stride zone

After years and years of studies, of characterization plans, of overlapping roles and skills, of bureaucratic impediments of various kinds, a concrete step is now being taken. The Undersecretary for Relations with Parliament, Matilde Siracusano, and the president of the Strait Port System Authority, Francesco Rizzo, are convinced of this. They don’t want to hear about “surrender” or “admission of impotence.” Rizzo even quotes Nietzsche: «The commissionership for the Falcata area is the exact opposite of a surrender, it is a “will to power”, it is the demonstration that today in Messina politics, bodies and institutions are all rowing towards the same objective: returning the Sickle to the people of Messina».
Press conference on Sunday, to allow the undersecretary to be present, given the commitments this week linked to the approval of the new budget law. And Matilde Siracusano immediately talks about funds, explaining that the total 22 million (of which 20 are the result of the amendment presented a few years ago by the Forza Italia MP) must be spent quickly and well, otherwise there is a risk of losing them. This is why the path of commissionership was identified, with special powers assigned to the president of the system Authority, following the model of the Recovery Law. Procedures will be able to be speeded up, the Authority will truly be able to act as a control room, also involving other bodies and institutions (from the Region to the Municipality), intervening with substitute powers in the event of non-compliance.
In praising this first concrete step, thanks to which it will be possible to start remediation in the contaminated sites of the Falcata area, the protagonists themselves admit that it is only a beginning, that the challenge will be much more demanding and the path will be neither short nor easy. It has been calculated that it will take between 80 and 100 million, in addition to the 22 already available, to complete the environmental remediation and carry out the urban regeneration projects.

But today what matters, and what Siracusano and Rizzo – together with the managers of the System Authority, the members of the Management Committee and the mayor Federico Basile himself (who wanted to give a sign of the attention of the entire city, even if, due to a strange paradox, the Municipality has no, if not residual, powers over the Scythe) – reaffirm with determination is that we are finally starting. And it was not easy to arrive at the commissionership decree, because – explains Matilde Siracusano – it was necessary to reach an agreement between Mit, Mef and Mase, that is, the three ministries of Transport, Economy and the Environment. And above all it was necessary to convince the MIT that, although it was not a question of infrastructural or transport works, but of urban regeneration, the intervention on the Falce di Messina should be considered a priority for the port system Authority and for the entire city.
The recovery program of the Falcata area, as explained by the president-commissioner, pursues three main objectives: safety and reclamation, regeneration and functional enhancement. To reach the goal, as mentioned, it is necessary to imagine a 100-120 million euro plan.
What can we do with the 22 million in cash? Meanwhile, the elimination of the main sources of contamination, within the identified perimeter, which includes the areas of the former degasification plant, the former shipyards, the sports field, the former San Raineri incinerator and the entire area that revolves around the Royal Citadel, as well as the stretch of sea in front, where the “Rigoletto” ship sank, the wreck of which must now be recovered and disposed of, because it represents one of the main sources of pollution. The timetable provides for the integrated contract, the executive project and the delivery of the works by the first quarter of 2027, with the use of 20 million euros obtained from the Development and Cohesion Funds and a further 2.5 million euros taken from the Authority’s budget.

Phase 2 will extend the reclamation also to the areas that will not be involved for now – think of the one occupied by the horrible former Eurobunker tanks, right next to the Montorsoli Lantern – and will include environmental, landscape and urban redevelopment projects “for the return to public use and urban, cultural and tourist-port functions”. «If we are good in the first phase, we will certainly obtain the resources to move forward», underlines Rizzo. And Matilde Siracusano agrees that it will be possible to draw on the considerable resources that the Government has allocated for the remediation of contaminated sites (in recent days 250 million euros were given to Campania for the rehabilitation of the “Land of Fires”). We will have to carry forward the “Falcata Revival” project and the one concerning the restoration and valorization of the 17th century fortress, a monumental symbol of the Falcata area, together with the Lanterna and Fort San Salvatore. At this moment, there is a worrying silence on the part of the Region and the Superintendence on the Royal Citadel: this is why the possibility of interventions for the president-commissioner becomes of fundamental importance, as provided for in the decree approved by the Chamber and which, this week, will also be approved by the Senate.
“We ask the city to support us in this great effort, which is a battle shared by all”, is the appeal launched by Rizzo, who among the various thanks to those who have worked and are working on this front, addressed a moving thought to those who, perhaps more than anyone, had made the recovery of the Royal Citadel and the Sickle one of the main reasons for living: the late Franz Riccobono.