The Botricello railway station is hostage to the works that Italian railway network, in its joints, has been carrying out without continuity for several years. A condition of absolute discomfort that is placing several problems of both hygiene health and public safety.
The situation is very complex, to the point that the mayor Saverio Simone Puccio It has issued an order, last year, to have safety, cleaning and reclamation of the construction site area in question, with the aim of preventing risks for health and public safety and protecting the urban decorum, forcing the parties involved to install specific self -supporting construction panels for the fence of the area.
The ordinance was compared only partially, while in the various interlocutions with the executing company of the works and with RFI herself has been repeatedly reiterated the need to complete the works that have been stopped for a long time.
However, nothing happened. Because of this, The mayor Puccio has again written to the company that manages the network to complete the works with the utmost urgency and cleanse and safety of the construction site itself.
“The attitude of RFI is not very collaborative – highlighted the mayor of Botricello – taking into account that several times we have urged interventions, to the point of duty directly to avoid dangers for public safety given the state of abandonment of the construction site. The situation is no longer tolerable and this forces us to activate all the institutional channels so that the necessary solutions are found, also applying any sanctions where expected”.
The mayor added how “it is not acceptable that RFI has maintained an unwell attitude, when it only claims rights for itself and obligations for the municipal body. At this point, we must intervene with determination, also in view of the summer season which, once again, risks being damaged by the endless construction site”.